Overview
Corrivo played a pivotal role in supporting Multiplex Construction during the final stages of the £430 million Elephant & Castle redevelopment project in London, a flagship regeneration scheme transforming a key South London destination.
When the principal cladding contractor unexpectedly entered liquidation near project completion, Corrivo stepped in to provide fast, expert support, ensuring lift cladding works could continue without significant disruption and helping keep the project on track for completion in early 2026.
About the Client & Project
Multiplex Construction (MPX) is a globally recognised contractor renowned for delivering complex, large-scale developments. Their Elephant & Castle scheme is one of London’s most significant regeneration projects, revitalising a major retail and transport hub in South London.
The development will deliver a vibrant mixed-use destination, incorporating:
- Modern retail and restaurant spaces
- Leisure facilities
- Contemporary workspace environments
- High-quality public realm improvements
With completion scheduled for early 2026, the project represents a major investment in the local community and infrastructure, making timely delivery essential.
Business Challenges
As the project neared completion, Multiplex encountered a significant and unexpected challenge. The appointed cladding contractor, responsible for design and installation, went into liquidation. This left several key areas of cladding work incomplete and meant that critical design drawings and technical documentation were either extremely limited or entirely unavailable. However, the programme’s deadlines remained fixed, leaving MPX under significant pressure to meet key delivery milestones.
This situation created a risk of delays, increased costs, and potential disruption to subsequent project phases. Multiplex required an experienced partner who could quickly step in, assess the situation, and design and deliver practical, buildable solutions.
Corrivo’s Solution
Corrivo responded immediately, mobilising technical expertise and resources to support the Multiplex team.
Key elements of Corrivo’s approach included:
Rapid Design Support
Corrivo provided urgent design solutions for key cladding and roofing elements, including Polyester Powder Coated (PPC) aluminium panels, supporting substructure (including stud welded and mechanically fixed stiffeners), closure flashings, soffit panels and copings.
Working with incomplete legacy information, the team quickly developed practical, compliant designs that could be implemented on site.
On-Site Collaboration
Close collaboration with the site team was critical. Corrivo conducted site visits and took detailed measurements to:
- Accurately assess unfinished areas
- Resolve discrepancies between existing installations and design intent
- Develop bespoke solutions for challenging sections of the build
Complex Detail Resolution
The project included intricate architectural features, such as curved flashing details, which required precise design and fabrication. Corrivo engineered tailored solutions to address these complexities without compromising quality or programme timelines.
Fast-Track Material Supply
To minimise disruption, Corrivo ensured a rapid turnaround on the fabrication and delivery of lift cladding materials and additional components. This enabled installation works to continue at pace, avoiding costly downtime.
Results & Benefits
Corrivo’s involvement delivered significant value to Multiplex and helped keep the wider project on track. Critical path activities were maintained, ensuring the programme remained aligned with its planned completion schedule. Their rapid mobilisation helped minimise disruption on site, reducing the impact caused by the cladding contractor’s insolvency. At the same time, Corrivo efficiently resolved complex design gaps despite limited access to original documentation, demonstrating strong technical problem-solving capabilities.
The new solutions were seamlessly integrated into the existing works, preserving design consistency across the project. This proactive and responsive approach also helped restore client confidence during what was a high-risk phase of the build. Ultimately, Corrivo’s ability to respond quickly, work collaboratively, and deliver practical solutions ensured that key areas of the project were completed on time.
Customer Testimonial
Liam Maze, Package Manager, and Michael Waters, Project Manager at Multiplex, praised Corrivo’s contribution:
“Corrivo’s rapid response and design support were critical during a very challenging period for the project. Their ability to step in, resolve complex issues, and keep works progressing made a significant difference. Without their support, we would not have been able to complete key areas in time to meet our project deadlines.”
Conclusion
This case study highlights Corrivo’s strength in responding to high-pressure project challenges. By combining technical expertise, agility, and collaborative working, Corrivo helped a global construction leader overcome a major delivery risk, keeping a flagship London development on track.